WOW , what a difference a week makes.
I was down here in early June to look at progress and came back again Friday 6/17 as I was in the area, and wanted a first hand update. Don't think any of us trust what management is telling us, so it was good to see with my own two eyes.
the last update I saw here someone posted 6/12 and said nothing had happened on bldgs 17-18-19-24-25.
Flash forward to Friday 6/17 and it looks like virtually ALL of the reinforcement of the walkways on ALL of these 5 buildings looks complete or nearly complete. GREAT NEWS....
See photos I took and compare the places with new lumber installed between the two dates. There is DEFINITE progress on buildings 17-18-19 and I think even 24-25 look to have had the 45 degree angle supports replaced. they look like they already had these 45 degree angle supports on 24-25 in my photos from 2 weeks ago, but that may have been existing wood from years ago. Whichever it is, the are now replaced. You can also see REALLY large horizontal beams on a regular basis under the floors of 2nd and 3rd floor all the way down from 25 to 17.
The stairways look about the same as the person who posted on 6/12, namely one stairway where the showers are that is complete from the parking lot up to the first floor.
There is construction material that appear to be future stairways and vertical supports for the stairs spread in front of all 5 of these buildings, and if you ask me, there's not that much of it remaining. It just doesn't look like it's a lot of work (or material) left to do to finish the stairs. Hopefully that means not much time needed to finish those stairs either.
As others have said though, waiting for the inspections and the certificate of occupancy is another matter. I will give them credit though, they do appear to be picking up speed as this cursed project seems to be in the home stretch.
I asked about dates in mid to late July for buidlings 17-18-19-24-25 at the registration area, but am not confident at all in the info the young lady gave me. Sorry, she just seemed to young and uninformed But her answer was an immediate "no way will they be ready in July."
I'm somewhat optimistic based on what I saw that this is wrapping up soon.
20160617_174104 by
NC Air, (new building by former bldgs 1-9 pool?) on Flickr
20160617_174051 by
NC Air, (backside of buildings 17-18-19)on Flickr
20160617_174030 by
NC Air, (sie of building 17) on Flickr
20160617_173939 by
NC Air, (buillding 19-18)on Flickr
20160617_173930 by
NC Air, (buillding 18-17)on Flickr
20160617_173923 by
NC Air, (buillding 19-18) on Flickr
20160617_173743 by
NC Air, (bldg 17-18-19-24) on Flickr
20160617_173737 by
NC Air, (bldg 25) on Flickr
20160617_173633 by
NC Air, (bldg 24) on Flickr
20160617_173630 by
NC Air, (bldg 24-25) on Flickr